DELHI GOLF CLUB LIMITED
Minutes of the meeting of the Green Sub Committee of
the Delhi Golf Club Limited held on Thursday, 5th February 2015 at
4.30 PM in the Board Room.
PRESENT
:-
Mr. Raj Khosla Captain/Chairman
Mr. Vikram
Sethi Co-Chairman
Capt.
Lalit Talwar
Lt.
Col. P.S. Bajaj
Mr. Pradeep
Jain SGDC
Mr. Anit
Mehrotra SGDC
Mr. Shubhash SGDC
Brig.
Sanjiv Mehra (Retd.) Secretary
Mr. Babu
Lall Sr.
Course Suptt.
Mr. Bhupendra
Singh Dy.
Manager Course
Mr.
Virendra Kumar Asst.
Course Suptt.
Leave of absence
was granted to the following Members:-
Mr. Vijay Kumar Topa Treasurer
1. CONFIRMATION OF MINUTES
OF THE MEETING HELD ON 16 JANUARY 2015.
The minutes were confirmed.
2. UPGRADATION OF PEACOCK
COURSE
The upgradation of the Peacock Course was discussed. The
members were satisfied with the progress made on the three holes viz 3,4 and 5 by SGDC Ltd. The
progress had also been reviewed by Mr. Vincent Pinto
of PCD earlier in the day. He had also expressed his satisfaction on the
standard and pace of work.
3. ROAD MAP FOR PEACOCK
COURSE
(a) The
Sub Committee discussed the options available for the next phase of the
proposed upgradation. The pros and cons of taking up
three holes at a time vis-s-vis
six holes in one phase were discussed. After detailed deliberation, the Sub
Committee decided to propose the upgradation of the
next six holes in one phase. The advantages of this are as under:-
(i)
The available machinery
will be optimally used and there will be a saving of overall cost due to no
escalation.
(ii)
There will be minimum
delay/ disruption due to the monsoons. The shaping and earthwork of all the
holes will be completed before the rains. The monsoon months will be used for
the grass to grow.
(iii)
Irrigation material has
been ordered for all the nine holes together.
(iv)
The entire course will
be available in a quicker time-frame.
(b) In
consultation with the representatives of SGDC, the following timelines were
agreed upon:-
(i)
The remaining holes of
the Peacock Course will be made available to SGDC by 25 February 2015.
(ii)
Hole
Nos.1, 2,3,4,5 and 6 will be handed over by SGDC to DGC on 30 August 2015.
(iii)
Hole
Nos. 7, 8 and 9 will be handed over by
30 November 2015.
(iv)
There will be no change
in rates.
(v)
The cost will be worked
out on the BOQ’s to be received from PCD.
(vi)
The 8th
fairway will serve as the nursery for the grass for all fairways. This will be
maintained by DGC.
(vii)
A separate contract
will be signed for this phase. SGDC needs to hire additional plant and
machinery for this work and for this mobilisation amount will be given to them.
4. COMPENSATION PACKAGE
FOR MEMBERS PLAYING ON THE PEACOCK COURSE
The
Sub Committee was of the opinion that there is a need for a policy to
temporarily adjust the
members utilising the Peacock Course. This will be worked out shortly.
BABU
LALL RAJ
KHOSLA
SR.COURSE SUPERINTENDENT CHAIRMAN